MATeF-2

MATeF – 2 Mission Status Flight electronics under testing TESTING Launch Date/Time: TBC Launch sight Recovery Date/Time: TBC TBD Lead Flight Director Chase Team Leader Bence Góczán TBD Radio Frequency Callsign 433MHz band TBC

Publications

Publications and Articles ESA Concurrent Engineering Workshop 2016 Posted on October 12, 2016 by admin ReHAB – 150 III – Flight Report Posted on April 25, 2016 by admin 1st Symposium on Space Educational Activities Posted on January 2, 2016 by admin ReHAB-150 II – GSBC Flight Posted on August 3, 2015 by admin ReHAB-150 […]

ReHAB – 150 III – Short Summary

On the 2nd of April 2016. we launched ReHAB – 150 balloon on the third time. The mission goals were to test the new software of the flight computer, take some pictures and test a prototype version of our ground station. The secondary goals, to test the 4.5 m dish antenna and rotator of BME-GND […]

ReHAB-150 III

ReHAB-150 III Mission Status Ready to fly READY TO LAUNCH Launch Date/Time: 02.04.2016. 09:00 (UTC) Launch sight Recovery Date/Time: 02.04.2016. 14:00 (UTC) (TBA) BME Building I Lead Flight Director Chase Team Leader Bence Góczán TBA Radio Frequency Callsign 433MHz band HA5MRC

GSBC flight short summary

On April 17th our Global Space Balloon Challenge flight took place. Our goal was to take pictures and send back some of them during flight via radio. Unfortunately we had to face some technical issues after launch. Our telemetry system stopped so we couldn’t get any signal from our primary tracking system. The balloon was […]

April 17th Flight

We are going to launch our balloon for Global Space Balloon Challenge on April 17th. Sue to some software issue we couldn’t test all the new modules. Only the new and improved OBC (On-Board Computer) module will fly. We will use the communication modul and power supply unit of the previous flight. We will test […]

Events of February

We’ve had a busy few weeks lately. On 12th February LEGO LAB has gathered its Semi-annual Project Night where Bence Góczán presented the latest developments and near future goals of our high altitude balloon project. Full gallery On 18th February Levente Pápay represented our team at the Szakmai Est presentation night of Simonyi Károly College […]

ReHAB – 150 II capsule Conceptional Plan

The animation below shows the step-by-step conceptual plan of the ReHAB-150 II capsule. It is shown how the UPRA Telemetry System and the cameras placed. The assembled capsule also gets a MLI coat that makes the insulation more efficent.

OBC near flight-complete state

After fixing the hardware problems the Internal Camera (ICC) is working again, now it is controlled by the flight version of the OBC. The camera got installed a fisheye lens that gives us wider field of view providing more exciting shots with the cam. Our next goal is to increse the quality of the pictures. […]